Architectural and development practices often have several sites going at once, each with its own site agent, subcontractors and handover date. Keeping one programme up to date across all of them is a job in itself.

Here's how this could run when your project lead keeps hold of every site's thread and tells you early when a handover date is in danger.

KardumoResidential sitesExample

Pieter · Mon 9 Mar, 07:45

We've got three sites on the go: 12 townhouses in Linden, 4 units in Parkhurst and 24 flats in Fourways. I want one programme across all of them, a short progress check-in from each site agent every day, and to know early when a handover is going to slip.

Your project lead · 07:48

I can set that up. I'll build the programme from the dates in your contracts and spreadsheets, then send each site agent a short check-in every afternoon at 15:30, due back by 17:00. It asks what was finished today, what's planned for tomorrow and how many days behind programme the site is.

One question for you

Should I ask Marius, your area manager, to check any site that's more than 5 days behind, or that sends nothing? He'd be emailed alongside your daily summary.

  • Yes, include Marius
  • Just me

How this could run for you

Here's how the first couple of months could go.

  1. Week 1

    One programme

    Pieter's project lead puts the three sites into one programme from the dates he already has. Pieter checks the handover dates and approves it.

  2. Every afternoon

    Check-ins from site

    Each site agent gets a short check-in at 15:30. They answer on their phones from site, and can attach photos or the latest snag list.

  3. Week 6

    An early warning

    Bongani's check-in from Fourways says the roof trusses will be two weeks late and puts the site 9 days behind programme. Because the programme shows what depends on them, the risk to the handover date is clear straight away.

  4. The same afternoon

    Options, not just bad news

    Pieter asks whether Fourways is still on track and gets the recovery options with their costs. The next morning, because Fourways is more than 5 days behind, Marius is asked to check it alongside Pieter's daily summary.

  5. Before the client meeting

    The programme report

    Pieter asks for a one-page view of all three sites, which he can print or save as a PDF for the meeting.

What you would see

These are the kinds of things your project lead sends, writes and answers along the way.

The daily site check-in

Site agents get the same short check-in every afternoon, at a time that suits site work. Photos and documents come back with the answers.

InboxBongani ZuluExample

Fourways flats: Today's site check-in

From
Kivo, project lead for Pieter van Wyk
To
Bongani Zulu, site agent, Fourways
Sent
Fri 17 Apr, 15:30

Hi Bongani,

Here's today's check-in for the Fourways site. It asks what was finished today, what's planned for tomorrow and how many days behind programme the site is. Please send it by 17:00.

You can attach photos or the updated snag list if that's easier than typing.

Answer today's check-in

Thanks,Kivo

This private link works for today's check-in only.

Is the handover on track?

When a delivery slips, your project lead works out what depends on it and how far the handover moves, then sets out the options for you to choose from.

KardumoFourways flatsExample

Pieter · Fri 17 Apr, 15:10

Is Fourways still on track for handover on 30 July?

Your project lead · 15:11

Not as things stand. The roof trusses now arrive on 3 May instead of 19 April, and the roof sheeting, ceilings and electrical second fix all wait on them. That moves handover to about 13 August.

What's slipping

ItemOwnerWas dueNow
Roof trusses deliveredTrusco, via Bongani19 Apr3 May
Roof sheeting finishedBongani Zulu7 May21 May

Ways to recover

  1. Start the ceilings in blocks A and B while block C waits for its trusses. Bongani thinks that saves about a week.
  2. Add a Saturday shift for the roofing team for four weeks. That's roughly R64 000 and brings handover back to around 2 August.

One decision for you

Which should go into the recovery plan?

  • Ceilings first
  • Saturday shifts
  • Both

The programme report

One page across every site, with handover dates, spend against budget and the decisions waiting on you. Spend is only as current as the figures people sent in.

KardumoProgramme reportOne pageExample

Programme across three sites

April · prepared for Pieter van Wyk

Where each site stands

SiteHandoverStatus
Linden, 12 townhouses18 JuneOn track
Parkhurst, 4 unitsSigned off on 9 AprilDone
Fourways, 24 flats30 July, likely 13 AugustAt risk

Spend against budget

  • LindenR14.2m of R21.5m
  • ParkhurstR7.9m of R8.1m
  • FourwaysR18.6m of R39m

Decisions needed

For you

Agree the Fourways recovery plan, and decide whether to tell the buyers' agent about a possible 13 August handover now or after the trusses arrive.

These are examples. The names, places and figures in them are made up.